Promised vs actual

Five projects, only the dates and dollars the record states.

By J Gonzales · Updated from the sourced tracker

Slip in days and budget variance stay not stated where the source gives a month, a phrase such as “about two months,” or a grant total on both sides.

Projects

Project Status Promised Revised Actual Slip (days) Budget variance Source
Relocated Fire Station 8 Completed late 2026-05 not stated 2026-07-21 not stated not stated 26-1045
New Fire Station 32 Slipped 2026-04 2026-09 not stated not stated not stated 26-1045
Police Training and Academy Facility Slipped 2025-12 2026-12 not stated not stated not stated 26-1045
Coyote Creek Flood Protection Project (Phase 2) On track 2028-12 not stated not stated not stated not stated 26-1099
Pure Water Silicon Valley (full-scale facility) On track 2035 not stated not stated not stated not stated 26-1100

The one dollar figure

Pure Water stores $3,295,950 as both the promised and actual amount. That is the grant total already cited ($1,092,000 and $2,203,950). The record does not state a construction variance, so the variance cell stays not stated. Source: 26-1100.